People & Events: Tunneling in the Sierra Nevada
Builders of the transcontinental railroad faced geographical
obstacles across the entire line. But none were quite as formidable
as the snowy granite mountain range rising east of Sacramento.
Getting through the Sierra Nevada would require fortitude,
technology -- and the sacrifice of many workers' lives.
The Big Obstacle
In August 1865 early snows defeated
the Central Pacific's initial attempt to begin work on Tunnel No. 6,
the Summit Tunnel. The grand engineering feat of the Sierra Nevada
would have to wait until the following year. Summer 1866 saw
construction of the Grizzly Hill and Emigrant Gap Tunnels (Tunnels
No. 1 and 2) west of Cisco. As fall approached, Chinese
crews were taken off other parts of the line and hurried once
more to the summit to get a jump on wintertime. Toil commenced on
the Donner granite of Tunnel No. 6 in August 1866, with men blasting
inward from what would become the east and west portals of the
passage. Progress with black powder through hard rock was
excruciatingly slow.
Four-Sided Approach
To speed progress, engineers
decided to drill a vertical shaft midway along the projected tunnel
line. Tunneling would take place on four faces at a time, as two
teams worked inward from the eastern and western ends of the tunnel
and two more teams worked back to back from the middle, moving
outward.Workers began clearing the 8-by-12-foot shaft on August 27
and made good progress for the first 30 days, at which point the job
of hoisting rubble from the shaft via hand derrick became too hard.
New Use for an Old Engine
Engineers found a solution in
the abandoned Sacramento, the locomotive that had taken the
first pioneering ride on Theodore
Judah's Sacramento Valley Railroad. Stripped of all
non-essential parts, it was driven to Gold Run, at that point the
end of the Central Pacific tracks. Its wheels were removed and its
body transferred to a logging truck driven by ten yoke of oxen. In a
dangerous and treacherous effort, the freight team hauled what
remained of the Sacramento -- a twelve-ton steam engine -- to
the top of Donner Pass, where it was let down carefully above Tunnel
No. 6 and housed in the large wooden enclosure now surrounding the
sunken shaft. The whole process took six weeks.
Massive Work Force
With the shaft completed, two
teams of Chinese workers descended to the middle of the rock and
began blasting the tunnel from the inside out. The steam engine was
employed to cart out their debris. On September 1, work finished on
the Emigrant Gap Tunnel (Tunnel No. 2), and those crews were
redistributed to the winter quarters and tunnel work waiting upon
the summit. That winter the men at Tunnel No. 6 were almost
completely Chinese, with a few Caucasians on the west end. Gangs
consisted of one white foreman per 30 or 40 workers, with each gang
working one of three rotating eight-hour shifts a day. An average of
six to ten thousand men worked on the railroad that winter, with as
many as 12,000 at one time.
Terrible Snows
A fierce winter in 1866-1867 brought
forty-four separate storms. The snow pack averaged eighteen feet at
the summit. "No one can face these storms when they are in earnest,"
Engineer John Gilliss recalled. The heaviest of them began on
February 18, 1867 and continued until February 22, when harsh winds
kept powder astir in the air until the snow started again days
later. The storm continued unabated until March 2. Drifts clogged
the entrance to every tunnel, turning many workers into full-time
shovelers. CP crews worked, ate, and slept in this inhospitable
environment, creating a network of tunnels under the snow to link
their camp sites with the work sites. The bad weather held up
provisions, diverted workers from railroad-building to
snow-management, and created a volatile, freezing world of
additional dangers.
Risks to Workers
The railroad lost uncounted men to
snow. Avalanches could cut down dozens at a time. "There was one
large snowslide at Strong's Canyon known as Camp 4. In this camp
were two gangs of Chinese for Tunnels 11 and 12, also a gang of
culvert men. The slide took it all, and one of the culvert men was
not found until the following spring," wrote Gilliss. Even when the
tunnels were done, maintaining them was a monumental task. In the
spring of 1868 most of the high-altitude tunnels were completely
blocked by ice, which had to be blasted loose and shoveled out. And
when snow wasn't killing men, the work was.
"Nitroglycerin Tells"
In total, the Central Pacific
engaged 11 tunnel projects (Nos. 3 through 13) in the Sierra that
winter. Seven of them clustered in a two-mile stretch east of Donner
Summit. Black powder was expensive, and its preparation
labor-intensive, requiring men to drill deep two-inch-wide holes by
hand in order to clear shallow amounts of rock. But progress
increased substantially on all fronts when British chemist James
Howden appeared in February 1867. He brought nitroglycerin,
which he mixed on location. The compound allowed for shallower holes
of narrow width, but its blasts achieved a much greater destructive
yield. Nitroglycerin debris was also much easier to move than the
debris of black powder, saving a lot of cumulative time and sweat.
Workers were able to advance up to two feet per day on all four
faces, instead of measuring each hard-won inch.
A Staggering Feat
With its rapidly accelerated pace,
the Central Pacific continued work on the Summit Tunnel into the
spring and summer of 1867. Workers broke through in August, just one
year after the vertical shaft had been drilled. Tunnel No. 6 was a
truly staggering feat of engineering. It measured 1,659 feet in
length, and reached, at its deepest, 124 feet into the rock. It sat
more than 7,000 feet above sea level. Calculations used to position
its end points and the central shaft were so accurate that the
workers found they were only two inches off when they broke through.
And it had been hand-carved, without electricity and without
steam-powered tools, except for the single old engine used to hoist
debris. The Union Pacific ramped up their track-laying speed and
built confidently into
Nevada, knowing their hardest task was behind them.
People & Events: Tunneling in the Sierra Nevada
© New content 1999-2003
PBS Online /
WGBH
|